Baltazar Contractors Inc. out of Ludlow, Mass is the low bidder at $6,006,220. The Town has $7 million in Other People's Money to get the job done. And the state--who is overseeing the project--will accept or reject the bid over the next 30 days.
Since the highway realignment project has been talked about since World War 2 ended, what's another 30 days?
If the bid is accepted the project--that includes two roundabouts--will take two years to complete.
Subscribe to:
Post Comments (Atom)
3 comments:
Two roundabouts Larry? I must have missed the news, I thought it was first said, one roundabout at the Atkins intersection....?
Yep. Two:
http://www.youtube.com/watch?v=SHpFkAi0fHU
Hey Larry!
Who else bid on the project and for what amounts? Could you give some figures?